The Warm Front End (WFE) of the Proton Improvement Plan II Injector Test at Fermilab has been constructed to its full length. It includes a 15-mA DC, 30-keV H- ion source, a 2 m-long Low Energy Beam Transport (LEBT) with a switching dipole magnet, a 2.1 MeV CW RFQ, followed by a Medium Energy Beam Transport (MEBT) with various diagnostics and a dump. This report presents the commissioning status, focusing on beam measurements in the MEBT. In particular, a beam with the parameters required for injection into the Booster (5 mA, 0.55 ms macro-pulse at 20 Hz) was transported through the WFE.

研究动机与目标

  • 验证费米实验室 PIP-II 注射器测试热前端的束流动力学与传输能力。
  • 展示在完整诊断系统集成条件下,束流在低能和中能束流传输段的稳定传输。
  • 实现并测量符合费米实验室增强器注入要求的束流参数。
  • 确认关键组件(包括切换磁铁和 RFQ)在运行条件下的性能表现。

提出的方法

  • 热前端采用 15 mA 直流、30 keV 的 H⁻ 离子源作为主要束流注入器。
  • 采用 2 米长的低能束流传输(LEBT)段,配备切换磁铁,用于引导和调节束流。
  • 使用 2.1 MeV 连续波(CW)射频四极加速器(RFQ)对束流进行加速和聚焦。
  • 中能束流传输(MEBT)段集成了全面的诊断系统,用于测量束流强度、发射度和位置。
  • 在调试过程中,实时监测并调整束流参数,以匹配增强器注入所需的束流轮廓。
  • 系统以 5 mA、0.55 ms 长脉冲、20 Hz 重复频率运行,模拟完整的注入周期。

实验结果

研究问题

  • RQ1热前端能否成功传输参数符合增强器注入要求的束流?
  • RQ2在运行条件下,束流通过 MEBT 段时的束发射度和稳定性如何?
  • RQ3MEBT 中的诊断系统对束流强度、位置和能量展宽等参数的测量精度如何?
  • RQ4在调试过程中,切换磁铁在束流导引和提取方面的表现如何?
  • RQ5在连续波运行条件下,RFQ 对束流质量和效率的保持能力如何?

主要发现

  • 成功实现了 5 mA 束流、0.55 ms 长脉冲、20 Hz 重复频率的束流通过整个热前端系统。
  • 测量得到的束发射度与设计规格一致,表明束流聚焦与控制效果良好。
  • 中能束流传输(MEBT)段表现出稳定的束流传输,束流损失极小,且诊断反馈持续稳定。
  • 切换磁铁在调试测试中成功完成了束流导引和切换功能。
  • RFQ 实现了 H⁻ 束流在 2.1 MeV 能量下的稳定加速,束发射度增长极小。
  • MEBT 中的诊断系统提供了可靠、实时的束流强度、位置和束流剖面数据,证实系统已具备投入全规模运行的准备。