[Paper Review] Analysis of Empirical Software Effort Estimation Models

M. S. Saleem Basha, P. Dhavachelvan|arXiv (Cornell University)|Apr 8, 2010
Software Engineering ResearchComputer Science27 references56 citations
TL;DR

This paper analyzes empirical software effort estimation models to evaluate their performance across diverse scenarios. Using comparative analysis with the Wilcoxon Signed-Rank Test, it concludes that no single estimation technique is universally optimal, and combining multiple models yields more reliable predictions.

ABSTRACT

Abstract – Reliable effort estimation remains an ongoing challenge to software engineers. Accurate effort estimation is the state of art of software engineering, effort estimation of software is the preliminary phase between the client and the business enterprise. The relationship between the client and the business enterprise begins with the estimation of the software. The credibility of the client to the business enterprise increases with the accurate estimation. Effort estimation often requires generalizing from a small number of historical projects. Generalization from such limited experience is an inherently under constrained problem. Accurate estimation is a complex process because it can be visualized as software effort prediction, as the term indicates prediction never becomes an actual. This work follows the basics of the empirical software effort estimation models. The goal of this paper is to study the empirical software effort estimation. The primary conclusion is that no single technique is best for all situations, and that a careful comparison of the results of several approaches is most likely to produce realistic estimates. Keywords-Software Estimation Models, Conte’s Criteria, Wilcoxon Signed-Rank Test.

Motivation & Objective

  • To investigate the effectiveness of various empirical software effort estimation models in predicting software development effort.
  • To address the inherent challenge of generalizing from limited historical project data in effort estimation.
  • To determine whether a single estimation technique consistently outperforms others across different scenarios.
  • To evaluate the credibility of effort estimates in strengthening client-business relationships in software projects.

Proposed method

  • The study evaluates multiple empirical software effort estimation models based on historical project data.
  • It applies Conte’s criteria to assess model quality and reliability in effort estimation.
  • Statistical comparison of model performance is conducted using the Wilcoxon Signed-Rand Test to identify significant differences.
  • The analysis focuses on prediction accuracy and consistency across diverse software development contexts.
  • Models are evaluated based on their ability to generalize from small historical datasets.
  • The methodology emphasizes comparative evaluation over reliance on a single estimation technique.

Experimental results

Research questions

  • RQ1Which empirical software effort estimation model performs best across diverse software development scenarios?
  • RQ2How does the performance of individual estimation models vary when compared using non-parametric statistical tests?
  • RQ3To what extent can generalization from limited historical data yield reliable effort estimates?
  • RQ4What is the impact of model selection on client trust and project credibility in software development?

Key findings

  • No single software effort estimation technique consistently outperforms all others across all scenarios.
  • Comparative evaluation of multiple models yields more realistic and reliable effort estimates than relying on a single method.
  • Statistical testing using the Wilcoxon Signed-Rank Test reveals significant performance differences between models.
  • Accurate effort estimation enhances client confidence and strengthens business relationships in software projects.
  • The prediction nature of effort estimation inherently limits its accuracy, making model comparison essential.
  • Empirical models based on historical data remain the foundation of effort estimation, but their reliability depends on methodological comparison.

Read this paper