Skip to main content
QUICK REVIEW

[Paper Review] LHC: status and commissioning plans

Michael R. E. Lamont|ArXiv.org|Jun 1, 2009
Superconducting Materials and ApplicationsEngineering5 references4 citations
TL;DR

This paper details the causes, repairs, and safety upgrades following the 2008 LHC sector 34 incident, which resulted from a faulty superconducting splice causing helium release and extensive damage. It outlines enhanced quench protection systems, improved splice monitoring, and mitigation measures to prevent recurrence, aiming for beam re-commissioning by late 2009 and delivering hundreds of pb⁻¹ of luminosity in the 2009–2010 run.

ABSTRACT

In 2008 the LHC saw a series of injection tests with beam and the start of full beam commissioning. Initial beam commissioning went well and circulating beam was quickly established. Progress was unfortunately curtailed by the sector 34 incident which caused extensive damage. The causes of the incident are recalled and the status of repairs and consolidation measures are presented. The schedule and luminosity targets for the 2009 - 2010 run are discussed.

Motivation & Objective

  • To analyze the root cause of the 2008 LHC sector 34 incident involving a faulty superconducting splice.
  • To document the extensive repair and consolidation measures taken to restore and strengthen the LHC magnet system.
  • To implement new quench protection and helium release mitigation systems to prevent recurrence of similar incidents.
  • To establish a revised commissioning plan for beam re-commissioning and luminosity delivery in the 2009–2010 run.
  • To ensure machine safety and reliability for high-energy proton collisions with improved diagnostics and quality assurance.

Proposed method

  • Identified the root cause as a high-resistance splice (220 nΩ vs. nominal 0.3 nΩ) leading to thermal runaway and helium release.
  • Executed a large-scale repair involving removal and reinstallation of 53 main magnets, including dipoles and quadrupoles, and refurbishment of cryogenic and vacuum systems.
  • Designed and deployed an extended Quench Protection System (QPS) with voltage monitoring at diode taps to detect splices with resistance >50–100 nΩ.
  • Installed new relief valves (DN200) and spring-actuated release paths in selected sectors to mitigate maximum credible incident (MCI) helium release.
  • Implemented rigorous quality assurance and testing protocols for all reinstalled circuits and components before cool-down.
  • Planned a phased beam commissioning process starting with low-intensity, un-squeezed beams, progressing to higher intensity and colliding beams.

Experimental results

Research questions

  • RQ1What caused the sector 34 incident in the LHC, and what were the physical mechanisms leading to the helium release and damage?
  • RQ2How can the risk of similar failures be mitigated through improved detection and protection systems in superconducting magnet circuits?
  • RQ3What are the key technical and operational challenges in repairing and re-commissioning a damaged LHC sector after a major incident?
  • RQ4What luminosity targets and beam parameters are feasible for the 2009–2010 LHC run under the revised safety and operational constraints?
  • RQ5How can the LHC ensure reliable and safe operation with high-intensity beams while minimizing the risk of future quench events?

Key findings

  • The sector 34 incident was caused by a defective splice with 220 nΩ resistance, far exceeding the nominal 0.3 nΩ, leading to resistive heating and thermal runaway.
  • A total of 53 main magnets (39 dipoles, 14 quadrupoles) were removed and replaced, with extensive repairs to cryogenics, vacuum, and insulation systems.
  • The extended Quench Protection System was designed to detect splices with resistance ≥50–100 nΩ, with a detection threshold of 300 µV over 10 seconds.
  • New relief valves (DN200) were installed in four sectors, and spring-actuated release paths were added to remaining cold sectors to mitigate MCI helium release.
  • The 2009–2010 run targeted delivery of 200–300 pb⁻¹ of good data, with first collisions expected around October 2009 and beam energy at 5 TeV.
  • Luminosity optimization was constrained by beam intensity limits (up to 5×10¹³ protons with tight collimation), β* limits (1–3 m in ATLAS/CMS, 2–4 m in LHCb), and the need for crossing angle use above 156 bunches.

Read this paper

Open the full text in the Nubint reader and ask about any passage as you read.

Read this paper on Nubint

This review was generated by AI from the original paper. Please check the paper before citing it.