The VERITAS collaboration relocated Telescope 1 to improve array symmetry and sensitivity, achieving a 30% improvement in sensitivity and a 60% reduction in observation time needed to detect a source. This was achieved through telescope relocation and concurrent optical PSF enhancement via a novel mirror alignment system, making VERITAS the most sensitive VHE array in the world for detecting faint sources like the 1% Crab nebula in under 30 hours.
The first VERITAS telescope was installed in 2002-2003 at the Fred Lawrence Whipple Observatory and was originally operated as a prototype instrument. Subsequently the decision was made to locate the full array at the same site, resulting in an asymmetric array layout. As anticipated, this resulted in less than optimal sensitivity due to the loss in effective area and the increase in background due to local muon initiated triggers. In the summer of 2009, the VERITAS collaboration relocated Telescope 1 to improve the overall array layout. This has provided a 30% improvement in sensitivity corresponding to a 60% change in the time needed to detect a source.
Motivation & Objective
- To improve the sensitivity of the VERITAS very high energy (VHE) gamma-ray telescope array by relocating Telescope 1 to a more optimal position.
- To reduce background contamination and increase effective collection area by minimizing overlap and redundancy between Telescopes 1 and 4.
- To enhance the optical point spread function (PSF) through a novel mirror alignment system, improving image quality and sensitivity.
- To minimize downtime during the upgrade by scheduling the relocation during the summer observing break.
- To maintain or improve angular and energy resolution while increasing overall array performance.
Proposed method
- Relocated Telescope 1 approximately 200 meters eastward from its original position near Telescope 4 to achieve a more symmetric array layout.
- Replaced the original asymmetric array (with 35 m separation between Telescopes 1 and 4) with a new layout where inter-telescope distances ranged from 81 m to 127 m.
- Implemented a new mirror alignment system to improve the optical PSF by 25–30%, enhancing image reconstruction and shower parameter resolution.
- Conducted a three-level trigger system: pixel-level, pattern trigger (3 adjacent pixels), and array trigger (2 or more telescopes within a time window).
- Performed simulations and simulations-based sensitivity analysis to predict performance gains before and after relocation.
- Scheduled the move during the summer shutdown (May 4 to September 4, 2009) to minimize disruption to the observing program.
Experimental results
Research questions
- RQ1What is the impact of Telescope 1's original close proximity to Telescope 4 on VERITAS sensitivity and background levels?
- RQ2How much sensitivity improvement can be achieved by relocating Telescope 1 to a more symmetric position in the array?
- RQ3To what extent does the improvement in optical PSF contribute to the overall sensitivity gain?
- RQ4What is the expected reduction in observation time for detecting a 1% Crab nebula signal after the upgrades?
- RQ5How do the angular and energy resolution metrics compare between the old and new array configurations?
Key findings
- The relocation of Telescope 1 resulted in a 30% improvement in integral flux sensitivity above 300 GeV.
- The time required to detect a 1% Crab nebula signal decreased from 48 hours to 28 hours, representing a 60% reduction in observation time.
- The sensitivity improvement corresponds directly to a 60% reduction in the time needed to achieve a 5σ detection for a given source flux.
- The energy resolution and angular resolution at 70 degrees elevation remained consistent with the original array configuration, indicating no degradation in core performance metrics.
- The optical PSF improvement contributed significantly to the sensitivity gain, with a 25–30% enhancement in image quality.
- VERITAS achieved the capability to detect a 1% Crab signal in less than 30 hours post-upgrade, making it the most sensitive VHE array at the time.