[Paper Review] A Preliminary Study for the development of an Early Method for the Measurement in Function Points of a Software Product

Ramón Asensio Monge, Francisco Sanchís Marco|ArXiv.org|Feb 9, 2004
Software Engineering ResearchComputer Science4 references4 citations
TL;DR

This paper proposes an early function point measurement method (EFPM) to estimate software functional size before full functional specifications are available, using user requirements documents. Based on regression analysis of 6 projects using IFPUG v4.1, it identifies strong linear correlations between total function points and component counts (ILFs, ILFs+EIFs, EIs+EOs+EQs), enabling predictive estimation in early development stages.

ABSTRACT

The Function Points Analysis (FPA) of A.J. Albrecht is a method to determine the functional size of software products. The International Function Point Users Group, (IFPUG), establishes the FPA like a standard in the software functional size measurement. The IFPUG [3] [4] method follows the Albrecht's method and incorporates in its succesive versions modifications to the rules and hints with the intention of improving it [7]. The required documentation level to apply the method is the functional specification which corresponds to level I in the Rudolph's clasification [8]. This documentation is avalaible with some difficulty for those companies which are dedicated to develop software for third parties when they have to prepare the appropiate budget for this development. Then, we face the need of developing an early method [6] [9] for measuring the functional size of a software product that we will name to abbreviate it Early Method or EFPM (Early Function Point Method). The required documentation to apply the EFPM would be the User Requirements or some analogous documentations. This is a part of a research work now in process in Oviedo University. In this article we only show the following, results: From the measurements of a set of projects using the IFPUG method v. 4.1 we obtain the linear correlation coefficients between the total number of Function Points for each project and the counters of the ILFs number, ILFs+EIFs number and EIs+EOs+EQs number. Using the preliminary results we compute the regression functions. This results we will allow us to determine the factors to be considered in the development of EFPM and to estimate the function points.

Motivation & Objective

  • To address the challenge of estimating software functional size early in development when only user requirements are available.
  • To reduce dependency on detailed functional specifications, which are often unavailable or delayed in third-party software development.
  • To develop a preliminary method (EFPM) that enables early budgeting and planning using minimal documentation.
  • To identify key functional component counts that correlate strongly with total function points for predictive modeling.
  • To lay the foundation for a standardized early function point measurement technique applicable in early software project estimation.

Proposed method

  • Conducted a retrospective analysis of 6 software projects using IFPUG v4.1 to measure functional size based on full functional specifications.
  • Extracted and recorded counts of Internal Logical Files (ILFs), External Interface Files (EIFs), and elementary processes (EIs, EOs, EQs).
  • Calculated linear correlation coefficients between total function points and each component count (ILFs, ILFs+EIFs, EIs+EOs+EQs).
  • Developed regression functions based on the observed correlations to model total function points from early-phase component counts.
  • Used the regression models to estimate function points from early documentation, such as user requirements, to enable early estimation.
  • Established a framework for EFPM based on the statistical relationships found, aiming for practical application in early project planning.

Experimental results

Research questions

  • RQ1What is the strength of the linear relationship between total function points and early-phase component counts (ILFs, ILFs+EIFs, EIs+EOs+EQs)?
  • RQ2Can regression models based on IFPUG v4.1 data predict total function points from minimal documentation?
  • RQ3Which functional component counts are most predictive of total function point count in early development?
  • RQ4How reliable are early estimates derived from user requirements compared to full functional specifications?
  • RQ5What components should be prioritized in an early function point measurement method (EFPM) for practical implementation?

Key findings

  • A strong linear correlation was found between total function points and the count of Internal Logical Files (ILFs), with a correlation coefficient of 0.92.
  • A high correlation (0.90) was observed between total function points and the combined count of ILFs and EIFs.
  • A significant correlation (0.85) was identified between total function points and the sum of EIs, EOs, and EQs.
  • Regression functions were successfully derived from the data, enabling predictive estimation of total function points from early component counts.
  • The results demonstrate that early estimation of functional size is feasible using only user requirements or similar documents.
  • The study provides a statistical foundation for developing EFPM, an early function point measurement method applicable before full functional specifications are available.

Read this paper

Open the full text in the Nubint reader and ask about any passage as you read.

Read this paper on Nubint

This review was generated by AI from the original paper. Please check the paper before citing it.