[Paper Review] Design and behaviour of the Large Hadron Collider external beam dumps capable of receiving 539 MJ/dump
This paper presents the design, analysis, and upgrade of the Large Hadron Collider's external beam dumps capable of absorbing 539 MJ per beam, addressing dynamic vibrations and structural fatigue caused by intense beam impacts. Using Monte Carlo beam interaction simulations and advanced thermo-mechanical finite element analysis, the study identified high-frequency vibrations (exceeding 200 g) as the root cause of mechanical failures, leading to a redesigned support system, beam windows, and radiation-resistant lubrication to ensure safe operation during LHC Run 3 and future high-luminosity upgrades.
Two 6-t beam dumps, made of a graphite core encapsulated in a stainless steel vessel, are used to absorb the energy of the two Large Hadron Collider (LHC) intense proton beams during operation of the accelerator. Operational issues started to appear in 2015 during LHC Run 2 (2014-2018) as a consequence of the progressive increase of the LHC beam kinetic energy, necessitating technical interventions in the highly radioactive areas around the dumps. Nitrogen gas leaks appeared after highly energetic beam impacts and instrumentation measurements indicated an initially unforeseen movement of the dumps. A computer modelling analysis campaign was launched to understand the origin of these issues, including both Monte Carlo simulations to model the proton beam interaction as well as advanced thermo-mechanical analyses. The main findings were that the amount of instantaneous energy deposited in the dump vessel leads to a strong dynamic response of the whole dump and high accelerations (above 2000g). Based on these findings, an upgraded design, including a new support system and beam windows, was implemented to ensure the dumps' compatibility with the more intense beams foreseen during LHC Run 3 (2022-2025) of 539 MJ per beam. In this paper an integral overview of the operational behaviour of the dumps and the upgraded configurations are discussed.
Motivation & Objective
- Address operational failures in LHC beam dumps during Run 2, including nitrogen leaks and unexpected mechanical movements due to increasing beam energy.
- Investigate the root cause of structural and dynamic issues in the dump system, particularly high-frequency vibrations and fatigue in beam windows and support structures.
- Design and validate an upgraded dump system compatible with 539 MJ beam energy during LHC Run 3, ensuring long-term reliability in a high-radiation environment.
- Develop advanced instrumentation and analysis techniques to monitor and predict dump behavior under extreme thermal and mechanical loads.
- Establish design principles and analysis methodologies applicable to future high-energy beam dumps for FCC, ILC, or CLIC.
Proposed method
- Employed Monte Carlo simulations (e.g., FLUKA) to model proton beam interactions and energy deposition in graphite and steel components.
- Conducted finite element analysis (FEA) with dynamic and quasi-static loading to assess thermo-mechanical response of the dump vessel and beam windows.
- Integrated beam load as time-dependent thermal and mechanical input into FEA models, simulating the 89 μs beam impact duration.
- Performed fatigue assessment using rainflow counting and damage accumulation models (Miner’s rule) on structural components under cyclic loading.
- Designed and tested a new support system using steel wire ropes with dual lubrication: Elaskon® SK-DL for initial corrosion protection and Lubrilog® LX AGFA 2 for radiation resistance.
- Conducted accelerated fatigue testing on degreased and greased rope samples under 2 Hz vibration to simulate operational conditions and validate safety margins.
Experimental results
Research questions
- RQ1What causes the unexpected mechanical movements and nitrogen leaks in the original LHC beam dumps at beam energies above 320 MJ?
- RQ2How does the instantaneous energy deposition from a 539 MJ proton beam impact generate dynamic vibrations in the dump system?
- RQ3What are the dominant stress sources in the beam window—direct beam impact or vibration-induced loads from the dump vessel?
- RQ4How can the fatigue life of the support system and beam windows be ensured under 539 MJ beam dumps and 15 MGy radiation exposure?
- RQ5What lubrication strategy ensures long-term performance of steel wire ropes in high-temperature, high-radiation environments?
Key findings
- The dump vessel experiences dynamic accelerations exceeding 200 g due to instantaneous thermal expansion from beam impact, causing high-frequency vibrations.
- Stresses in the beam windows are dominated by vibration transmission from the dump vessel rather than direct beam impact, making dynamic response the primary design concern.
- Fatigue analysis of the support system shows a safety factor greater than 10 under operational conditions, even with complete loss of lubrication.
- Accelerated fatigue testing on degreased rope samples confirmed 2.24 million cycles with an effective breaking force of 413.7 kN, validating the design life.
- The dual-lubrication strategy—Elaskon® SK-DL for initial protection and Lubrilog® LX AGFA 2 for radiation resistance—was selected to mitigate degradation under 15 MGy and 100°C.
- Instrumentation installed post-upgrade successfully records displacements and vibrations, enabling validation of future analyses and design for HL-LHC (680 MJ/dump).