[Paper Review] Why are Megaprojects, Including Nuclear Power Plants, Delivered Overbudget and Late? Reasons and Remedies

Giorgio Locatelli|arXiv (Cornell University)|Feb 16, 2018
Nuclear and radioactivity studiesEngineering26 citations
TL;DR

This paper investigates why megaprojects, especially nuclear power plants, are consistently over budget and delayed, identifying optimism bias, poor planning, and lack of standardization as root causes. It proposes that Small Modular Reactors (SMRs) can mitigate these issues through dual standardization—technical design and project delivery chains—enabling repeatable, scalable deployment that improves cost and schedule performance.

ABSTRACT

In the first section, this report analyses Nuclear Power Plants (NPPs) in the context of megaprojects, explaining why they are often delivered over budget and late. In the second section, the report discusses how Small Modular Reactors (SMRs) might address these issues. Megaprojects are extremely risky and often implemented after a sub-optimal phase of project planning leading to underestimations of the costs and overestimation of short-term benefits. When considering adherence to schedule and budget, often megaprojects might be considered a failure, and optimism bias, strategic mis-rapresentation, complexity, poor planning, poor risk allocation, poor scope management are all reasons to explain their over budget and delay. For megaprojects, especially in the nuclear field, a key strategy to achieve good performances appears to be the standardization. This standardization needs to be twofold: (i) technical standardisation, i.e. the construction of very similar design over and over, and (ii) the project delivery chain standardisation, i.e. the same stakeholders involved in the delivery of a project that is replicable multiple times. Under this perspective, given their size and standardisation potential, SMRs, might be a suitable class of NPP for several countries. Yet, if the economy of scale is the only driver considered, SMRs are hardly competitive with large NPPs (or even with gas or coal power plants). However, a fleet of standard SMRs might balance the lack of economy of scale with the economy of multiples, and the delivery of several standardised SMR projects might be the key to achieve good project management performances in the nuclear sector. However, the deployment of SMRs faces a number of challenges from several perspectives, such as the licencing, supply chain and financing ones. These challenges might be enormous, but so are the potential rewards too.

Motivation & Objective

  • To analyze the systemic reasons behind cost overruns and delays in megaprojects, particularly nuclear power plants.
  • To identify the role of poor project planning, risk mismanagement, and strategic misrepresentation in megaproject failures.
  • To evaluate whether Small Modular Reactors (SMRs) can overcome these challenges through standardization of design and delivery processes.
  • To assess the feasibility of achieving better project performance in nuclear energy through fleet-based deployment of standardized SMRs.
  • To examine the challenges—licensing, supply chain, financing—hindering SMR deployment despite their potential benefits.

Proposed method

  • Analyzes historical data from megaprojects, including nuclear power plants, to identify recurring patterns of cost and schedule overruns.
  • Applies the concept of 'optimism bias' and 'strategic misrepresentation' as behavioral and institutional drivers of underestimation in project planning.
  • Proposes a dual standardization framework: (i) technical standardization of reactor design and (ii) standardization of project delivery chains involving repeatable stakeholders.
  • Evaluates the economic viability of SMRs not by individual plant scale, but by fleet deployment to achieve 'economy of multiples' as a counterbalance to lack of economies of scale.
  • Uses case studies and comparative analysis of large NPPs versus SMR deployment models to assess project performance potential.
  • Considers institutional and regulatory barriers such as licensing complexity and financing structures that impede SMR scalability.

Experimental results

Research questions

  • RQ1What are the primary causes of cost overruns and schedule delays in megaprojects, particularly nuclear power plants?
  • RQ2How does optimism bias and strategic misrepresentation contribute to project planning failures in large infrastructure projects?
  • RQ3To what extent can standardization of reactor design and project delivery processes improve megaproject outcomes in the nuclear sector?
  • RQ4Can Small Modular Reactors (SMRs) achieve better cost and schedule performance than large nuclear power plants through fleet-based deployment?
  • RQ5What are the key institutional and financial barriers to the widespread adoption of SMRs despite their theoretical advantages?

Key findings

  • Megaprojects, including nuclear power plants, are frequently delivered over budget and late due to optimism bias, strategic misrepresentation, poor risk allocation, and inadequate planning.
  • Standardization of both reactor design and project delivery chains is identified as a critical enabler for improving project performance in nuclear energy projects.
  • While SMRs do not achieve economies of scale per unit, fleet deployment of standardized SMRs can generate an 'economy of multiples' that improves overall cost and schedule predictability.
  • The success of SMRs depends on replicable project delivery models involving consistent stakeholders and processes, not just technological standardization.
  • Despite significant potential, SMR deployment faces major challenges in licensing, supply chain development, and financing, which must be addressed to unlock benefits.
  • The report concludes that standardized, fleet-based SMR programs represent a viable pathway to achieving reliable, on-budget, and on-time nuclear energy projects.

Read this paper

Open the full text in the Nubint reader and ask about any passage as you read.

Read this paper on Nubint

This review was generated by AI from the original paper. Please check the paper before citing it.