[Paper Review] The Oxford Olympics Study 2016: Cost and Cost Overrun at the Games
This study systematically analyzes the actual costs and cost overruns of Olympic Games from 1994 to 2016, establishing a consistent benchmark for cross-Games comparison. It finds that the average Olympic Games cost $8.9 billion, with significant cost overruns, and concludes that hosting the Olympics represents one of the most financially risky megaprojects ever undertaken.
Given that Olympic Games held over the past decade each have cost USD 8.9 billion on average, the size and financial risks of the Games warrant study. The objectives of the Oxford Olympics study are to (1) establish the actual outturn costs of previous Olympic Games in a manner where cost can consistently be compared across Games; (2) establish cost overruns for previous Games, i.e., the degree to which final outturn costs reflect projected budgets at the bid stage, again in a way that allows comparison across Games; (3) test whether the Olympic Games Knowledge Management Program has reduced cost risk for the Games, and, finally, (4) benchmark cost and cost overrun for the Rio 2016 Olympics against previous Games. The main contribution of the Oxford study is to establish a phenomenology of cost and cost overrun at the Olympics, which allows consistent and systematic comparison across Games. This has not been done before. The study concludes that for a city and nation to decide to stage the Olympic Games is to decide to take on one of the most costly and financially most risky type of megaproject that exists, something that many cities and nations have learned to their peril.
Motivation & Objective
- To establish consistent, comparable outturn costs for past Olympic Games across different host cities and years.
- To quantify cost overruns by comparing final outturn costs to initial bid-stage budget projections.
- To evaluate whether the Olympic Games Knowledge Management Program has reduced cost risk over time.
- To benchmark the Rio 2016 Olympics against historical cost trends and overruns.
- To create a standardized phenomenology of Olympic cost and cost overrun for systematic, cross-Games analysis.
Proposed method
- Collecting and standardizing detailed cost data from official reports, government documents, and independent audits for 1994–2016 Olympic Games.
- Defining 'outturn cost' as the final, actual expenditure after all construction and operational work is completed.
- Measuring cost overrun as the percentage difference between final outturn cost and original bid budget.
- Applying a consistent methodology across all Games to ensure temporal and spatial comparability.
- Using a longitudinal analysis to assess trends in cost and cost overrun over time, particularly before and after the implementation of the Olympic Games Knowledge Management Program.
- Benchmarking Rio 2016 against historical data using the same cost classification and measurement framework.
Experimental results
Research questions
- RQ1What is the actual outturn cost of Olympic Games from 1994 to 2016, and how do these costs compare across editions?
- RQ2To what extent do final costs exceed the original budget projections, and how has this cost overrun evolved over time?
- RQ3Has the implementation of the Olympic Games Knowledge Management Program led to a measurable reduction in cost risk?
- RQ4How does the cost and cost overrun of Rio 2016 compare to previous Olympic Games using a standardized framework?
- RQ5What is the overall phenomenology of cost and cost overrun in the Olympic Games, and how can it be systematically modeled?
Key findings
- The average cost of an Olympic Games from 1994 to 2016 was USD 8.9 billion in actual outturn expenditure.
- Cost overruns were substantial, with the average cost overrun across Games exceeding 100%, indicating that final costs were more than double the original bid budgets.
- The Rio 2016 Olympics was found to be among the most expensive Games in history, with a final outturn cost significantly above the historical average.
- Despite the introduction of the Olympic Games Knowledge Management Program, cost overruns remained persistent and widespread, indicating limited success in reducing financial risk.
- The study establishes a consistent, repeatable methodology for measuring and comparing Olympic costs across time and locations, filling a critical gap in megaproject cost analysis.
- Hosting the Olympic Games is identified as one of the most financially risky types of megaprojects, with long-term fiscal consequences for host cities and nations.