[Paper Review] Optimal Generation and Transmission Expansion Planning Addressing Short-Term Constraints with Co-optimization of Energy and Reserves
This paper proposes a mixed-integer linear programming (MILP) model for integrated generation and transmission expansion planning that co-optimizes investment and operational decisions under hourly chronological constraints, including unit commitment, ramping, and reserve requirements. The model uses representative typical days and sub-horizon decomposition to maintain computational tractability while accurately capturing the variability of renewable energy and short-term system constraints.
The penetration of variable renewable energy (VRE) in electrical systems has changed the way the expansion planning is treated. This kind of resource has great variability in small amounts of time, which makes it important to represent hourly constraints that require chronology. Besides that, the generation reserves should also be adjusted in order to capture the intermittent effect, and since many countries use rapid thermal plants as part of these reserves, unit commitment and ramp constraint have also become more significant. In this paper, we propose a MILP expansion planning model that can represent hourly time steps while maintaining reasonable computational times, where both investment and operation problems are simultaneously solved. Because the planning horizons are long (decades), the resolution of the entire horizon in a single optimization problem would be computationally infeasible for large real systems, making it necessary, therefore, to apply a horizon decomposition heuristic in smaller sub-horizons, and use the representation of typical days and seasons to reduces the size of the problem.
Motivation & Objective
- To address the growing complexity of power systems with high variable renewable energy (VRE) penetration by incorporating short-term operational constraints into long-term expansion planning.
- To co-optimize investment and operational decisions—specifically unit commitment, ramping, and reserve requirements—within a single mixed-integer linear programming (MILP) framework.
- To maintain computational feasibility for large-scale systems by using representative typical days and horizon decomposition instead of full chronological modeling.
- To improve planning accuracy by explicitly modeling hourly variability of renewables and the need for operating reserves.
- To enable more reliable and cost-effective expansion plans in renewable-dominated power systems by accounting for non-convex operational constraints.
Proposed method
- The model employs a multi-stage, multi-scenario MILP formulation that integrates investment and operational decisions over a long-term planning horizon.
- It uses representative typical days per season to reduce problem size, replacing full-year hourly simulation with a manageable set of representative days.
- The planning horizon is decomposed into sub-horizons to improve computational tractability while maintaining temporal consistency.
- The model explicitly includes binary variables for unit commitment and ramping constraints, enabling accurate representation of thermal plant start-ups and output changes.
- Reserve requirements are co-optimized with energy dispatch, ensuring that sufficient spinning and regulation reserves are available in each time period and scenario.
- Hydro reservoir operations are modeled with penalty terms for violations of minimum storage, turbining, and outflow constraints, while avoiding full stochastic dynamic programming.
Experimental results
Research questions
- RQ1How can long-term generation and transmission expansion planning be improved by integrating hourly operational constraints such as unit commitment and ramping?
- RQ2To what extent can representative typical days and sub-horizon decomposition maintain solution accuracy while reducing computational burden in large-scale expansion planning?
- RQ3What is the impact of co-optimizing energy and reserve dispatch on investment decisions in systems with high renewable penetration?
- RQ4How does the omission of full hydrological stochasticity affect the optimality and reliability of the expansion plan?
- RQ5What trade-offs exist between computational complexity and scenario resolution in co-optimized expansion planning models?
Key findings
- The model successfully co-optimizes investment and operation decisions, enabling accurate representation of unit commitment and ramping constraints through binary variables in a MILP framework.
- Using typical days instead of full-year simulation reduces computational complexity while preserving key temporal dynamics of renewable generation and load.
- The inclusion of reserve co-optimization ensures that required spinning and regulation reserves are systematically provided in each time period and scenario.
- The model demonstrates computational feasibility for real-world systems by decomposing the planning horizon into sub-horizons and using representative days.
- Despite the omission of full stochastic dynamic programming for hydro, the model shows satisfactory performance in investment decision-making, though with a potential optimistic bias in reservoir operation.
- The computational cost increases significantly with the number of scenarios, limiting scalability for very large systems with high scenario resolution.