[Paper Review] Should we build more large dams? The actual costs of hydropower megaproject development
This paper uses reference class forecasting to analyze actual cost and schedule overruns in large hydropower dams, revealing systematic underestimation in planning. It finds that without robust risk management, most large dams are economically unviable due to 44–99% cost overruns and 60–66% schedule slippage, urging policymakers to favor agile, smaller-scale energy alternatives.
A brisk building boom of hydropower mega-dams is underway from China to Brazil. Whether benefits of new dams will outweigh costs remains unresolved despite contentious debates. We investigate this question with the "outside view" or "reference class forecasting" based on literature on decision-making under uncertainty in psychology. We find overwhelming evidence that budgets are systematically biased below actual costs of large hydropower dams - excluding inflation, substantial debt servicing, environmental, and social costs. Using the largest and most reliable reference data of its kind and multilevel statistical techniques applied to large dams for the first time, we were successful in fitting parsimonious models to predict cost and schedule overruns. The outside view suggests that in most countries large hydropower dams will be too costly in absolute terms and take too long to build to deliver a positive risk-adjusted return unless suitable risk management measures outlined in this paper can be affordably provided. Policymakers, particularly in developing countries, are advised to prefer agile energy alternatives that can be built over shorter time horizons to energy megaprojects.
Motivation & Objective
- To investigate the actual financial and scheduling performance of large hydropower dams using empirical data.
- To address the persistent problem of cost and schedule underestimation in megaproject planning.
- To evaluate whether large dams deliver positive risk-adjusted returns under realistic cost and time projections.
- To provide a transparent, evidence-based framework for policymakers to assess energy project viability.
- To advocate for agile, shorter-horizon energy alternatives over large-scale hydropower megaprojects.
Proposed method
- Applies reference class forecasting (RCF), an 'outside view' approach based on decision-making under uncertainty, to predict project outcomes.
- Uses the largest and most reliable dataset of completed large hydropower dams to establish a reference class for cost and schedule performance.
- Employs multilevel statistical models (Models 1, 2, and 3) to predict cost and schedule overruns while accounting for country-specific and project-specific variables.
- Compares ex ante (planning) estimates with actual outcomes to quantify systematic biases in cost and time forecasting.
- Uses per capita income, dam wall length, and installed capacity as key predictors in multilevel models to forecast overruns.
- Tests the robustness of forecasts using both global reference class data and country-specific modeling (e.g., Pakistan vs. the US for Diamer-Bhasha).
Experimental results
Research questions
- RQ1To what extent are cost and schedule estimates for large hydropower dams systematically biased below actual outcomes?
- RQ2What is the actual cost overrun and schedule slippage experienced by large hydropower dams globally?
- RQ3Can reference class forecasting reliably predict cost and schedule overruns for new large dam projects?
- RQ4Under what conditions do large dams fail to deliver a positive risk-adjusted return?
- RQ5How do economic and institutional factors (e.g., per capita income) influence the magnitude of cost and schedule overruns?
Key findings
- Large hydropower dams systematically suffer from cost overruns, with actual costs exceeding initial estimates by 44% to 99% in constant prices.
- Schedule overruns are substantial, with a 66% average overrun needed to achieve 80% confidence in on-time completion.
- For the Diamer-Bhasha dam in Pakistan, the model predicts a 60% schedule overrun, pushing completion to 2027 despite a planned 2021 completion.
- Even under optimistic benefit estimates, the Diamer-Bhasha dam’s net present value benefit-to-cost ratio falls below 1 after de-biasing costs.
- In contrast, a similar dam in the US would face only a 0.05% schedule slippage, highlighting the role of national economic capacity in project performance.
- The study concludes that large dams are unlikely to yield positive risk-adjusted returns unless affordable, effective risk management measures are implemented.
Read this paper
Open the full text in the Nubint reader and ask about any passage as you read.