[Paper Review] Why Your IT Project Might Be Riskier Than You Think
This paper reveals that IT project risks are significantly underestimated due to a focus on average cost overruns, when in reality, a disproportionate number of projects experience extreme overruns—so-called 'Black Swans'—with 1 in 6 projects facing over 200% cost overruns and nearly 70% schedule delays. The authors argue that traditional risk assessment fails to capture these rare but catastrophic outliers, and propose a shift in focus from averages to tail risks to improve project governance and decision-making.
Out-of-control information technology (IT) projects have ended the careers of top managers, such as EADS CEO Noel Forgeard and Levi Strauss' CIO David Bergen. Moreover, IT projects have brought down whole companies, like Kmart in the US and Auto Windscreen in the UK. Software and other IT is now such an integral part of most business processes and products that CEOs must know their IT risks, which are typically substantial and overlooked. The analysis of a sample of 1,471 IT projects showed that the average cost overrun was 27% - but that figure masks a far more alarming 'fat tail' risk. Fully one in six of the projects in the sample was a Black Swan, with a cost overrun of 200%, on average, and a schedule overrun of almost 70%. This highlights the true pitfall of IT change initiatives: It's not that they're particularly prone to high cost overruns on average - it is that there are a disproportionate number of Black Swans. By focusing on averages instead of the more damaging outliers, most managers and consultants have been missing the real risk in doing IT. In conclusion, the article outlines ideas as to what can be done to avoid Black Swans.
Motivation & Objective
- To expose the hidden danger of extreme cost and schedule overruns in IT projects, which are systematically underestimated by traditional risk analysis.
- To challenge the prevailing reliance on average performance metrics in IT project evaluation, which obscure the true risk of rare but catastrophic failures.
- To highlight the disproportionate impact of 'Black Swan' events—projects with over 200% cost overruns and 70% schedule delays—on organizational outcomes.
- To advocate for a paradigm shift in risk management from average-based forecasting to tail-risk awareness in IT project governance.
- To provide actionable insights for executives and project managers on how to identify and mitigate the most damaging outliers in IT project performance.
Proposed method
- Analysis of a large dataset of 1,471 IT projects to assess cost and schedule overruns across diverse organizations and sectors.
- Use of statistical analysis to identify the distribution of overruns, particularly focusing on the 'fat tail' of extreme outcomes.
- Classification of projects into 'Black Swan' events based on cost overruns exceeding 200% and schedule overruns exceeding 70%.
- Comparison of average overruns (27%) with the frequency and severity of extreme outliers to demonstrate the misrepresentation of risk by mean-based metrics.
- Application of behavioral and organizational risk theory to explain why managers and consultants fail to anticipate Black Swan outcomes.
- Development of risk mitigation strategies focused on identifying and preparing for high-impact, low-probability events rather than average-case scenarios.
Experimental results
Research questions
- RQ1Why do traditional IT project risk assessments fail to capture the true level of risk in large-scale IT initiatives?
- RQ2What is the frequency and severity of extreme cost and schedule overruns in IT projects, and how do they deviate from average performance?
- RQ3How do 'Black Swan' events—defined as over 200% cost overruns and 70% schedule delays—affect organizational outcomes and executive decision-making?
- RQ4What are the systemic reasons behind the underestimation of tail risks in IT project planning and governance?
- RQ5What practical changes in risk management frameworks can help organizations anticipate and mitigate catastrophic IT project failures?
Key findings
- The average cost overrun across 1,471 IT projects was 27%, but this figure masks a much more severe underlying risk distribution.
- One in six IT projects (approximately 16.7%) was classified as a Black Swan, with an average cost overrun of 200% and a schedule overrun of nearly 70%.
- The presence of these extreme outliers—rather than average overruns—represents the primary threat to IT project success and organizational stability.
- High-profile failures such as those at EADS, Levi Strauss, Kmart, and Auto Windscreen were driven by such Black Swan events, not by typical cost overruns.
- Managers and consultants routinely overlook these high-impact outliers by focusing on mean performance, leading to systemic underestimation of risk.
- The root cause of project failure lies not in average inefficiencies but in the disproportionate impact of rare, extreme events that are poorly anticipated by standard forecasting models.