[Paper Review] Minimizing Makespan in Sublinear Time via Weighted Random Sampling

Bin Fu, Yumei Huo|arXiv (Cornell University)|Feb 3, 2026
Scheduling and Optimization AlgorithmsEngineering0 citations
TL;DR

The paper presents two sublinear-time randomized approximation schemes for makespan minimization on m identical machines using weighted random sampling, yielding (1+ε)-approximate makespans and sketch schedules for known and unknown n.

ABSTRACT

We consider the classical makespan minimization scheduling problem where $n$ jobs must be scheduled on $m$ identical machines. Using weighted random sampling, we developed two sublinear time approximation schemes: one for the case where $n$ is known and the other for the case where $n$ is unknown. Both algorithms not only give a $(1+3ε)$-approximation to the optimal makespan but also generate a sketch schedule. Our first algorithm, which targets the case where $n$ is known and draws samples in a single round under weighted random sampling, has a running time of $ ilde{O}( frac{m^5}{ε^4} \sqrt{n}+A(\ceiling{m\over ε}, ε ))$, where $A(\mathcal{N}, α)$ is the time complexity of any $(1+α)$-approximation scheme for the makespan minimization of $\mathcal{N}$ jobs. The second algorithm addresses the case where $n$ is unknown. It uses adaptive weighted random sampling, % extit{that is}, it draws samples in several rounds, adjusting the number of samples after each round, and runs in sublinear time $ ilde{O}\left( frac{m^5} {ε^4} \sqrt{n} + A(\ceiling{m\over ε}, ε ) ight)$. We also provide an implementation that generates a weighted random sample using $O(\log n)$ uniform random samples.

Motivation & Objective

  • Develop sublinear-time randomized algorithms for the classical makespan minimization problem on m identical machines.
  • Leverage weighted random sampling to handle imbalanced job sizes and reduce input dependency.
  • Provide sketch schedules and enable post-hoc construction of concrete schedules with near-optimal makespan.

Proposed method

  • Use weighted random sampling where each job’s sampling probability is proportional to its processing time.
  • Construct a sublinear-size input sketch that groups jobs by estimated processing-time intervals and preserves key OPT(I) properties.
  • Apply a meta-algorithm that uses a black-box (1+α)-approximation scheme on the largest jobs and batches the rest to achieve (1+ε)-approximation.
  • Ensure the sketch is (α,β1,β2)-sketch, with guarantees on counts per interval and the sketch’s OPT, enabling sublinear-time computation of OPT(I).
  • Differentiate algorithms for known n (single-round sampling) and unknown n (adaptive weighted sampling).
  • Provide a method to derive a sketch schedule from the sketch and to extend it to a full schedule when all data is available.

Experimental results

Research questions

  • RQ1Can makespan on m identical machines be approximated within (1+ε) in sublinear time using weighted sampling?
  • RQ2How to construct a compact sketch of the input that preserves the essential makespan structure for both known and unknown n?
  • RQ3How can a general (1+α)-approximation algorithm be composed with a sketch to yield a (1+ε)-approximation for the original instance?
  • RQ4What are the running-time guarantees and sketch-size bounds for known vs unknown n scenarios?

Key findings

  • For known n, there is a randomized (1+ε)-approximation algorithm running in tilde-O(m^5/ε^4 * sqrt(n) + A(ceil(m/ε), ε)) time.
  • For unknown n, there is a randomized (1+ε)-approximation algorithm running in tilde-O(m^5/ε^4 * sqrt(n) + A(ceil(m/ε), ε)) time.
  • The algorithms produce a sketch schedule represented with space O(m^2/ε^2 * log(mn^2)) (known n) or O(m^2/ε^2 * log(nm/ε)) (unknown n), enabling later concrete scheduling with makespan at most (1+3ε)OPT(I).
  • The approach combines weighted sampling, generalized birthday paradox arguments, and black-box approximation schemes for makespan minimization to achieve sublinear-time solutions.
  • A practical implementation is provided to generate weighted samples using O(log n) uniform samples.
  • Sketch-based methodology allows converting the sketch schedule into a full schedule once full job information is available.

Read this paper

Open the full text in the Nubint reader and ask about any passage as you read.

Read this paper on Nubint