[Paper Review] Scheduling Post-Disaster Repairs in Electricity Distribution Networks
This paper proposes a computationally efficient scheduling framework for post-disaster repair in radial electricity distribution networks, using a time-indexed integer programming model with valid inequalities and three heuristic algorithms: LP-based list scheduling, a single-to-multi-crew conversion algorithm, and a $ρ$-factor-based dispatch rule. The key contribution is a $(2 - \frac{1}{m})$-approximation conversion algorithm that outperforms exact ILP solutions in speed and solution quality on large-scale test systems.
Natural disasters, such as hurricanes, earthquakes and large wind or ice storms, typically require the repair of a large number of components in electricity distribution networks. Since power cannot be restored before these repairs have been completed, optimally scheduling the available crews to minimize the cumulative duration of the customer interruptions reduces the harm done to the affected community. Considering the radial network structure of the distribution system, this repair and restoration process can be modeled as a scheduling problem with soft precedence constraints. As a benchmark, we first formulate this problem as a time-indexed ILP with valid inequalities. Three practical methods are then proposed to solve the problem: (i) an LP-based list scheduling algorithm, (ii) a single to multi-crew repair schedule conversion algorithm, and (iii) a dispatch rule based on $ρ$-factors which can be interpreted as Component Importance Measures. We show that the first two algorithms are $2$ and $\left(2 - \frac{1}{m} ight)$ approximations respectively. We also prove that the latter two algorithms are equivalent. Numerical results validate the effectiveness of the proposed methods.
Motivation & Objective
- Address the challenge of minimizing cumulative customer interruption duration after natural disasters by optimally scheduling multiple repair crews in radial distribution networks.
- Formulate the repair scheduling problem as a time-indexed integer linear program (ILP) with soft precedence constraints due to radial network topology.
- Develop practical, fast algorithms suitable for real-time or near real-time deployment when detailed damage information becomes available.
- Provide theoretical performance guarantees for heuristic algorithms and validate them on standard IEEE distribution test systems.
- Demonstrate that component importance measures ($\rho$-factors) can guide effective repair prioritization in multi-crew scenarios.
Proposed method
- Formulate the post-disaster repair problem as a time-indexed mixed-integer linear program (MILP) with valid inequalities to strengthen the relaxation.
- Propose an LP-based list scheduling algorithm that uses the optimal solution of the LP relaxation to guide repair sequencing, achieving a 2-approximation guarantee.
- Introduce a conversion algorithm that transforms an optimal single-crew repair sequence into a multi-crew schedule, proven to be a $(2 - \frac{1}{m})$-approximation for $m$ crews.
- Develop a $ρ$-factor-based dispatch rule that assigns repair priorities based on component importance, equivalent in performance to the conversion algorithm.
- Apply the algorithms to IEEE 123-node and 8500-node test feeders to evaluate solution quality and computational efficiency.
- Use the ellipsoid method to solve the LP relaxation with exponentially many constraints, enabling performance benchmarking against the ILP.
Experimental results
Research questions
- RQ1Can a time-indexed ILP formulation with valid inequalities effectively model post-disaster repair scheduling in radial distribution networks with soft precedence constraints?
- RQ2How do LP-based list scheduling and conversion-based multi-crew scheduling algorithms compare in terms of solution quality and computational efficiency?
- RQ3Can a $ρ$-factor-based dispatch rule, interpreted as a component importance measure, achieve performance equivalent to the conversion algorithm?
- RQ4What is the trade-off between solution quality and computation time when solving the exact ILP versus heuristic methods on large-scale distribution networks?
- RQ5To what extent does the proposed framework improve network functionality at intermediate restoration times compared to standard industry practices?
Key findings
- The conversion algorithm achieved a harm value of $2.2751 \times 10^3$ on the IEEE 123-node system, outperforming the ILP’s $3.0788 \times 10^3$ in under one second.
- On the IEEE 8500-node system, the conversion algorithm solved the problem in 150.64 seconds with a harm of $7.201 \times 10^5$, while the LP relaxation took over 60 hours to solve.
- The LP-based list scheduling algorithm achieved a 2-approximation bound and provided a better solution than the ILP in 24 seconds on the 123-node system.
- The $ρ$-factor-based dispatch rule resulted in approximately 10% more network functionality restored halfway through the process compared to standard industry practices.
- The conversion algorithm and the $ρ$-factor-based rule were proven to be mathematically equivalent in performance, validating the importance of component-level priority metrics.
- The ILP model was infeasible for large-scale networks due to excessive computation time, highlighting the necessity of heuristic approaches for real-time deployment.