[Paper Review] Coordinating Distributed Energy Resources for Reliability can Significantly Reduce Future Distribution Grid Upgrades and Peak Load

Thomas Navidi, Abbas El Gamal|arXiv (Cornell University)|Jun 14, 2023
Smart Grid Energy ManagementEngineering3 citations
TL;DR

This paper proposes a centralized, reliability-optimized control scheme for distributed energy resources (DERs) that significantly reduces distribution grid infrastructure upgrades and peak load. Using a power flow-driven simulation-optimization framework, it shows that coordinating DERs for grid reliability—rather than just cost—reduces transformer violations from 81% to 28% and peak load by 17%, with only a 5.1% increase in electricity cost by 2050.

ABSTRACT

Current DER coordination schemes, such as demand-response and VPPs, aim to reduce electricity costs during peak demand events with no consideration of distribution grid reliability. We show that coordinating DERs for grid reliability can significantly reduce both the infrastructure upgrades needed to support future increases in DER and electrification penetrations and peak load. Specifically, using a power flow driven simulation-optimization methodology, we compare the potential reliability improvements with a perfect-foresight centralized DER controller that minimizes reliability violations to a local controller that minimizes consumer electricity cost. We find, for example, that by 2050 with local control, on average 81% of the transformers in a distribution grid experience violations, compared to 28% with centralized control, which simultaneously reduces peak load by 17%. These reductions are achieved with only 5.1% increase in electricity cost. These findings suggest that future incentives for DER adoption should include reliability coordination.

Motivation & Objective

  • To quantify the impact of increased DER penetration and electrification on distribution grid reliability.
  • To compare the effectiveness of local (cost-minimizing) versus centralized (reliability-minimizing) DER control schemes.
  • To assess how DER coordination for reliability reduces the need for costly infrastructure upgrades and peak load.
  • To evaluate the sensitivity of results to flexible load availability, storage distribution, and EV charger power ratings.
  • To inform policy by demonstrating that reliability coordination should be a key incentive in future DER adoption strategies.

Proposed method

  • A power flow-driven simulation-optimization methodology is used, integrating a 3-phase distribution network model with time-resolved load and DER profiles.
  • The centralized controller solves a mixed-integer linear program to minimize a weighted sum of electricity cost, storage operation cost, voltage violations, and transformer overloading.
  • Constraints include limits on DER output, EV charging windows, battery charge/discharge rates, and thermal energy storage operation.
  • Voltage violations are defined as deviations >±5% from nominal voltage over 15-minute intervals per ANSI C84.1 standards.
  • Transformer overloading is measured as average apparent power exceeding 120% of rated capacity over 2-hour windows.
  • The simulation is run across 11 diverse U.S. distribution networks, with 16 scenarios per network, using OpenDSS for quasi-static power flow analysis.
Figure 1 : Block diagram of the power flow driven simulation and optimization methodology. User specified input data are described in the parallelograms; user specified control scheme in the hexagon; and simulation operations in the rectangles. Each item in the diagram is described in detail in the
Figure 1 : Block diagram of the power flow driven simulation and optimization methodology. User specified input data are described in the parallelograms; user specified control scheme in the hexagon; and simulation operations in the rectangles. Each item in the diagram is described in detail in the

Experimental results

Research questions

  • RQ1How much grid infrastructure upgrading will be required to support future DER and electrification growth under local control?
  • RQ2To what extent can centralized DER coordination for reliability reduce the need for distribution grid upgrades?
  • RQ3How does reliability-based DER control impact peak load and consumer electricity costs compared to cost-minimizing local control?
  • RQ4How do results vary with the availability of flexible loads, storage distribution, and EV charger power ratings?
  • RQ5What is the trade-off between reliability improvement and increased electricity cost under different control strategies?

Key findings

  • By 2050, local control leads to reliability violations in 81% of transformers, compared to only 28% under centralized reliability-optimized control.
  • Centralized DER coordination reduces peak load by 17% compared to local control, despite no explicit peak load objective.
  • The increase in electricity cost under centralized control is only 5.1% higher than under local control, indicating a favorable cost-reliability trade-off.
  • The centralized controller achieves a 65% reduction in required infrastructure upgrades by minimizing reliability violations across the network.
  • The results are robust across diverse U.S. distribution networks, with consistent improvements in voltage and thermal violation metrics.
  • The study demonstrates that reliability coordination is a highly effective, low-cost strategy to defer costly grid upgrades in future distribution systems.
(a) Percentage increase in total energy due to electrification.
(a) Percentage increase in total energy due to electrification.

Read this paper

Open the full text in the Nubint reader and ask about any passage as you read.

Read this paper on Nubint