[Paper Review] Different Cost Performance: Different Determinants? The Case of Cost Overruns in Dutch Transportation Infrastructure Projects
This study investigates cost overruns in Dutch transportation infrastructure projects, analyzing project type, size, and implementation phase length as determinants. It finds that pre-construction phase duration is the strongest predictor—each extra year increases cost overrun by 5 percentage points—while construction phase length has negligible impact, offering targeted insights for mitigating overruns in the Netherlands.
This paper examines three independent explanatory variables and their relation with cost overrun in order to decide whether this is different for Dutch infrastructure projects compared to worldwide findings. The three independent variables are project type (road, rail, and fixed link projects), project size (measured in terms of estimated costs) and the length of the project implementation phase. For Dutch projects, average cost overrun is 10.6% for rail, 18.6% for roads and 21.7% for fixed links. For project size, small Dutch projects have the largest average percentage cost overruns but in terms of total overrun, large projects have a larger share. The length of the implementation phase and especially the length of the pre-construction phase are important determinants of cost overruns in the Netherlands. With each additional year of pre-construction, percentage cost overrun increases by five percentage points. In contrast, the length of the construction phase has hardly any influence on cost overruns. This is an important contribution to current knowledge about cost overruns, because the period in which projects are most prone to cost overruns is narrowed down considerably, at least in the Netherlands. This means that period can be focused on to determine the causes and cures of overruns.
Motivation & Objective
- To examine whether determinants of cost overruns in Dutch transportation infrastructure projects differ from global patterns.
- To assess the impact of project type (road, rail, fixed link), size, and implementation phase length on cost overruns.
- To identify which phase of project development—pre-construction or construction—is most influential in driving cost overruns.
- To provide actionable insights for policymakers by narrowing the critical period for cost overrun causes.
Proposed method
- The study analyzes a dataset of Dutch transportation infrastructure projects, categorizing them by type (road, rail, fixed link), estimated cost, and duration of implementation phases.
- Cost overrun is measured as the percentage difference between final actual cost and initial estimated cost.
- Multiple regression analysis is used to assess the influence of project type, size, and length of pre-construction and construction phases on cost overrun.
- The analysis distinguishes between percentage cost overrun and total cost overrun to evaluate both relative and absolute financial impacts.
- The study compares findings to global trends in infrastructure cost overruns to assess contextual specificity.
Experimental results
Research questions
- RQ1Do the determinants of cost overruns in Dutch infrastructure projects differ from those identified in global studies?
- RQ2How does project type (road, rail, fixed link) influence the magnitude of cost overruns in the Netherlands?
- RQ3To what extent does project size affect cost overrun in terms of percentage and total financial impact?
- RQ4Is the length of the pre-construction phase a stronger predictor of cost overrun than the construction phase in Dutch projects?
- RQ5Can the pre-construction phase be identified as the primary period requiring intervention to reduce cost overruns?
Key findings
- Average cost overrun is 10.6% for rail projects, 18.6% for road projects, and 21.7% for fixed link projects in the Netherlands.
- Small projects exhibit the highest average percentage cost overruns, but large projects contribute the most to total cost overrun in absolute terms.
- Each additional year in the pre-construction phase increases cost overrun by 5 percentage points.
- The length of the construction phase has negligible influence on cost overrun, contrary to common assumptions.
- The pre-construction phase is the primary period of risk for cost overruns, making it a critical target for intervention.