[Paper Review] Underestimating Costs in Public Works Projects: Error or Lie?

Bent Flyvbjerg, Mette Skamris Holm|Oxford University Research Archive (ORA) (University of Oxford)|Mar 6, 2013
Construction Project Management and PerformanceDecision Sciences8 references234 citations
TL;DR

This paper analyzes 258 transportation infrastructure projects worth $90 billion and finds that cost overruns are systematically and significantly underestimated in project proposals. Using statistical analysis, the authors conclude that underestimation is not due to error but is best explained by strategic misrepresentation—i.e., lying—by project promoters, undermining the reliability of cost-benefit analyses for public decision-making.

ABSTRACT

This article presents results from the first statistically significant study of cost escalation in transportation infrastructure projects. Based on a sample of 258 transportation infrastructure projects worth US$90 billion and representing different project types, geographical regions, and historical periods, it is found with overwhelming statistical significance that the cost estimates used to decide whether such projects should be built are highly and systematically misleading. Underestimation cannot be explained by error and is best explained by strategic misrepresentation, that is, lying. The policy implications are clear: legislators, administrators, investors, media representatives, and members of the public who value honest numbers should not trust cost estimates and cost-benefit analyses produced by project promoters and their analysts.

Motivation & Objective

  • To investigate the causes of persistent cost overruns in public infrastructure projects.
  • To determine whether underestimation of project costs is due to error or intentional strategic misrepresentation.
  • To assess the reliability of cost-benefit analyses used in project approval processes.
  • To provide empirical evidence on the scale and pattern of cost underestimation across different project types and regions.
  • To inform policymakers and stakeholders about the trustworthiness of cost estimates produced by project promoters.

Proposed method

  • The study uses a dataset of 258 transportation infrastructure projects spanning different types, regions, and historical periods.
  • It compares initial cost estimates with actual final costs to measure the magnitude of cost escalation.
  • Statistical significance testing is applied to assess whether underestimation is systematic rather than random.
  • The analysis distinguishes between error-based explanations and strategic behavior, using evidence of consistent underestimation across diverse projects.
  • The researchers employ regression and inferential statistics to evaluate the likelihood of error versus deliberate misrepresentation.
  • The study draws on data from publicly available sources and official project records to ensure data integrity.

Experimental results

Research questions

  • RQ1Is cost underestimation in public infrastructure projects due to systematic error or strategic misrepresentation?
  • RQ2To what extent do cost estimates in project proposals consistently underestimate actual project costs?
  • RQ3Can the pattern of underestimation be explained by cognitive bias or by deliberate deception?
  • RQ4How does the magnitude of cost overruns vary across project types, regions, and time periods?
  • RQ5What are the implications of systematic underestimation for the validity of cost-benefit analyses in public investment decisions?

Key findings

  • The study finds overwhelming statistical significance that cost estimates for public works projects are systematically and highly misleading.
  • Underestimation of project costs cannot be explained by error and is best explained by strategic misrepresentation—i.e., lying.
  • The average cost overrun across the sample is substantial, with actual costs significantly exceeding initial estimates.
  • The pattern of underestimation is consistent across different project types, geographical regions, and historical periods.
  • The results indicate that cost-benefit analyses based on promoter-provided estimates are not trustworthy for public decision-making.
  • Legislators, investors, and the public should not rely on cost estimates produced by project promoters due to their inherent unreliability.

Read this paper