Nooshin Yousefi, Ahmad Sobhani|arXiv (Cornell University)|Feb 6, 2019
Construction Project Management and PerformanceDecision Sciences21 references2 citations
TL;DR

This paper proposes a two-step adjustment framework that applies statistical control charts to Earned Duration Management (EDM) indices to monitor project schedule performance, addressing non-normality and autocorrelation in project data. The method enhances early detection of schedule and cost deviations, improving project managers' ability to initiate corrective actions in time.

ABSTRACT

Monitoring of project performance is a crucial task of project managers that significantly affect the project success or failure. Earned Value Management (EVM) is a well-known tool to evaluate project performance and effective technique for identifying delays and proposing appropriate corrective actions. The original EVM analysis is a monetary-based method and it can be misleading in the evaluation of the project schedule performance and estimation of the project duration. Earned Duration Management (EDM) is a more recent method which introduces metrics for the project schedule performance evaluation and improves EVM analysis. In this paper, we apply statistical control charts on EDM indices to better investigate the variations of project schedule performance. Control charts are decision support tools to detect the out of control performance. Usually project performance measurements are auto-correlated and not following the normal distribution. Hence, in this paper, a two-step adjustment framework is proposed to make the control charts applicable to non-normal and auto-correlated measurements. The case study project illustrates how the new method can be implemented in practice. The numerical results conclude that that employing control chart method along with analyzing the actual values of EDM indices increase the capability of project management teams to detect cost and schedule problems on time

Motivation & Objective

  • To address the limitations of traditional Earned Value Management (EVM) in measuring schedule performance due to its monetary basis.
  • To improve project performance monitoring by applying statistical control charts to Earned Duration Management (EDM) indices.
  • To develop a two-step adjustment framework that enables control charts to be used with non-normal and autocorrelated project performance data.
  • To demonstrate the practical applicability and effectiveness of the proposed method through a case study.
  • To enhance the capability of project management teams to detect cost and schedule problems earlier and more accurately.

Proposed method

  • The study applies statistical control charts to EDM indices to detect out-of-control performance variations.
  • A two-step adjustment framework is proposed to handle non-normal and autocorrelated project performance measurements.
  • The first step involves transforming the EDM indices to reduce non-normality using statistical techniques.
  • The second step applies time series adjustments to account for autocorrelation in the performance data.
  • Control limits are recalculated based on adjusted data to maintain statistical validity.
  • The method is validated using a real-world case study to illustrate implementation and effectiveness.

Experimental results

Research questions

  • RQ1How can statistical control charts be effectively applied to EDM indices despite non-normal and autocorrelated data?
  • RQ2What adjustments are necessary to make control charts reliable for monitoring project schedule performance using EDM metrics?
  • RQ3To what extent does the proposed framework improve the detection of schedule and cost deviations compared to standard EDM analysis?
  • RQ4How does the integration of control charts with actual EDM index values enhance project management decision-making?
  • RQ5What are the practical implications of using this method in real project environments?

Key findings

  • The two-step adjustment framework successfully enables the use of control charts on non-normal and autocorrelated EDM indices, improving statistical reliability.
  • The application of control charts alongside actual EDM index values increases the sensitivity of detecting schedule and cost deviations.
  • The case study demonstrates that the method allows project managers to identify performance issues earlier than with EDM alone.
  • The framework supports timely corrective actions by distinguishing between common-cause and special-cause variations in project performance.
  • The results confirm that integrating control charts with EDM enhances the overall capability of project management teams to monitor and control project performance.
  • The method provides a robust, data-driven approach for continuous performance monitoring in complex, dynamic project environments.

Read this paper

Open the full text in the Nubint reader and ask about any passage as you read.

Read this paper on Nubint

This review was generated by AI from the original paper. Please check the paper before citing it.